Purchase Tickets

Budgets

THE TWO FIGURES USED MOST in the Bajagua debate are $66 million and $600 million. President Bush’s proposed budget for 2008 calls for $66 million to upgrade the International Wastewater Treatment Plant in San Ysidro to secondary standards. The $600 million figure was used by the U.S. General Accountability Office to describe the expected outlay associated with the Bajagua proposal. But the GAO figure didn’t give a breakdown of construction costs or an operations-and-maintenance budget, and Bajagua officials question it. Bajagua opponents, meanwhile, say the company hasn’t given a detailed rendering of its expected costs, either—all of which leaves a giant and contentious question surrounding the true costs that can be expected with both plans.

Bajagua spokesperson Craig Benedetto says comparing $66 million to $600 million is like comparing apples to oranges, and he’s right. The $66 million figure (generally considered far less than the true cost of upgrading the IWTP facility) is a one-time construction fee and doesn’t take into account interest, unknown variables or operations and maintenance costs for the next 20 years (as the Bajagua plan does).

Though Bajagua hasn’t given specific numbers on its expected building or operations costs, a set of spending parameters was outlined in the now-suspended development agreement it signed with the International Boundary and Water Commission. That pre-contract indicated Bajagua expected to have a total operating budget of $34 million a year for 20 years (a total price tag of $640 million). In the agreement, the company said it would strive to bring that figure down to $30 million per year ($600 million over 20 years; the GAO figure) but that it reserved the right to charge up to $39 million per year ($780 million over 20 years).

The upgrade at San Ysidro, meanwhile, will cost far more than the $66 million figure being bandied about. Most experts agree it will cost at least $100 million; figures from the IBWC’s 2005 Supplemental Environmental Impact Statement put the figure as high as $127 million. The $66 million appropriation in the president’s budget, if it passes Congress, will only start the upgrade. To make the apples-to-apples analogy accurate, operating costs for 20 years have to be added to that figure. One California wastewater expert believes that, if given the money to do the upgrades at the IWTP, the IBWC will install an activated-sludge system (more expensive to run than aerated ponds) and that the process could add an extra $3 million to $4 million to the plant’s yearly operating costs. Figures from the SEIS show the commission believes an aerated pond system will cost $4 million to run every year, and an activated-sludge system will cost $6 million.

Using the SEIS’ higher values, it will cost an estimated $60 million (of 2004 adjusted dollars) to run an aerated pond system for 20 years and $80 million to run an activated-sludge system. Adding that to the $8.41 million it’s averaged to run the IWTP over the past five years (information gleaned from a Freedom of Information Act request at the IBWC)—$168 million over 20 years—it will cost taxpayers an estimated $328 million to $348 million (depending on the system employed) to build and run an secondary treatment center at the IWTP for the next 20 years.

Of the IWTP’s original $234 million budget, $90 million paid for the state-of-the-art South Bay Ocean Outfall, $8 million went to the Army Corps of Engineers, and $9 million went to studies and other associated costs; only $127 million of that outlay was directed to building the actual plant. Add to that $127 million to the $328 million to $348 million figure, and the expected 20-year cost to upgrade and run the plant is $455 million to $475 million.

However, the $127 million capital cost has already been paid, meaning the true cost to taxpayers will be $328 million or $348 million over 20 years. That figure, compared to Bajagua’s projected money flows—$600 million to $780 million over 20 years—is the apples-to-apples comparison.

The SEIS does a far more thorough job and investigates a number of engineering and economic impacts on eventual costs. It estimates that the three options involving a Bajagua-built Mexican plant would cost taxpayers $29.3 million to $29.7 million per year. The two IWTP upgrade options (aerated ponds or activated sludge), it says, would cost taxpayers $17.5 million and $21.6 million per year, for 20 years.

The SEIS (and other information regarding Bajagua and international \water issues) is available at the IBWC Web site (www.ibwc.state.gov/) and at www.ibwc.state.gov/Files/SBIWTPFinalSEIS.pdf.

Newsletter

Subscribe to our email newsletters to get updates on local news, events and opportunities in San Diego. Please enter your email address below:

Email
I am interested in receiving email updates about:
(Choose one or more categories)
The "A" List
The Weekender
The Main Dish
Travels
San Diego At Home
Art of Giving
Party Invites
Exquisite Weddings

Features

Sweet Surrender

There’s no better time——or excuse——than the holidays to indulge your chocolate craving.

Firestorm 2007

Surviving and Thriving in the Worst of Times, The Fire Diary, The Q Contrast, and Smoke, Ashes and Spirit

Dashing Through the Sand

A photographic tour of a bedecked San Diego illustrates our distinct SoCal holiday style.

A Sewer Runs Through It

The murky tale surrounding the Bajagua Company and its controversial plan to build——and profit from——a multimillion-dollar wastewater treatment plant south of the border to deal with...

Departments

Restaurant Reviews
Foodie Gossip
Nightlife
Wine Reviews
Tom Blair's I on San Diego
Publisher's Letter
Inside
Letters
Front Pages
Dialogue with Tom Blair
Journal
Business
San Diego Style
Seen
Agenda
Art
Calendar
Stage
Best Bets
View all articles in this issue »